|

STAKEHOLDER UPDATE DECEMBER 2009
The meeting was poorly attended maybe the dark cold night
had something to do with it.
It was an interesting meeting with presentations by
Lost Arts who are
doing the Bandstand. We were shown the new design for the
Cafe and Bowling club. Its hoped this can go before planning
before Xmas and then tenders can be sought in the new year
with work starting in March time.
One exiting piece of news is that the play area has been
brought forward due to complaints and the horse and spider
falling apart. Designed by children it will be divided into
two areas one for very young children and one for older
children. Its hoped it will be ready for easter next year so
thats good new all round and it shows the council do take
notice of people.
Its still hoped that the lake will be finished by March next
year and open to the public at long last but some paths will
have to be closed in the future for new paths to go in.
Chairmans report
Lake and Bridge Works (Tolent Construction)
Tolent have been on site for 11 wks following acceptance of
their tender.
There has been a 6 day delay due to bad weather.
The Tolent site will close at Xmas from 18th Dec for 2 wks.
Works have focused on lake edges and islands plus
preparations for bridge abutments and foundations etc.
The Inlet Bridge at the Tipkinder end of the lake is the
first bridge to go in and it will arrive on site Tue / Wed
next week, preparation works are ongoing.
All Lake Inlet walls have been repaired and repointed.
Gabion baskets all around the Burma Star Island to be faced
with stone blocks. A stone sample has been agreed.
East and West Island walls have been completed but may be
raised to allow fluctuations in water levels.
Works to modify bridge abutments are underway.
Broadwalk Bridge works on site for 3 days next week. This
will be the last and largest bridge to be positioned
estimate end of Feb. Footpath links will need to go in to
facilitate all bridges.
Coronation Bridge - Completion is expected by the end of
January - together with Burma Star Bridge.
Problem areas:
• Access roads require improving.
• Weather implications.
• Design modifications and approvals.
• Correction of Wrekin works where required.
BANDSTAND
Slight slippage of works largely due to discoveries on site
and additional higher quality finishes which have been
agreed. Matching of sandstone to closely match the original
has been very successful.
A detailed update and explanation of how these structures
are restored will be given by Domenic of Lost Art. The
completion date will now be end of January 2010.
NB. Ian will be providing a detailed update on the Lake and
Bridge works and progress with the bandstand.
PLAYGROUND
Rocking horse and spider's web removed due to safety
implications see above.
An exciting consultation took place involving the Sir
William Stanier Community School and their feeder school's
i.e. children talking to younger children. The selection and
design process is well underway. Additional monies via ex
Mayor will be allocated specifically for the disabled
element. A contractor will be selected early spring2010.
COUNTY LANDSCAPES
Curved railings are to be completed early in the New Year
and the Gates will be the very last item due to heavy
construction vehicles accessing the park to install the
bridges.
EVENTING
A very successful community Youth Christmas Lantern
Procession took place last Sunday. It attracted approx 300
people; we were very pleased with the response. Pupils of
Pebble Brook, Monks Coppenhall, Edleston Road and Wistaston
schools all participated.
We have a relation of Dick, Charles who is trying to find any information on
him or any photos if you have anything please contact us
Born at Broughty Ferry in 1838, he served an apprenticeship from 1854
under James How at Monifieth Foundry. After short times as a workman
in the marine-engine shops of J. & G. Thomson on the Clyde and of James Jac
k & Co at Liverpool, he was taken-on in the Crewe erecting shops in August
1860 after walking to that place from Liverpool in search of work.
In 1862, while a chargehand erector, he attracted the attention of young
Webb at the evening classes of the Mechanics Institute where he won a prize.
Webb brought him into the office as a temporary tracer and draughtsman, and
in 1863 he became an established member of the drawing office staff at 8s 4d [42p]
a day. He succeeded Kampf as chief draughtsman on 15 December 1871 at a salary
of £160 a year raised in steps to £225 at the end of 1874 and, as he himself wrote,
with heavy work and long hours. Under his charge were developed the designs of the
Webb Precursors, Precedents and coal engines.
In February 1877 he was appointed manager of the signal department at Crewe; he
had manufacture, installation and maintenance in his care, with much outdoor wor
k along the line in all weathers. G. P. Neele, the LNWR traffic superintendent,
paid him compliments for his signal work in Railway Reminiscences ( 1902).
In February 1882 he succeeded Worsdell as works manager, though the appointment
was still styled indoor assistant. He died on 2 June 1888 of chest and kidney
complaints at the age of 50, but in essence he was worn out by the work and its
responsibilities following his hard and often penurious youth. In reporting his
death to the Locomotive Committee Webb said "he was a very able and faithful
servant of the Company." A grant of six months' salary, less amount paid on
sick leave, was given to his four children aged 23 to 14, for he was a widower.
Dick came to take much part in Crewe local affairs. He was deputy mayor to Webb
in the Jubilee year of 1887, and presided at the public dinner to celebrate the
Queen's Jubilee and Crewe's railway jubilee, for Webb as mayor of the borough
was away at the national thanksgiving service in Westminster Abbey. He was treasure
r of the Mechanics Institute 1875-81. After Dick's death in 1888 a shelter was
erected in the then new Queen's Park i
n memory of him; he himself had supervised the layout of the park.
Webb and Dick always got on well together and were much of an age.
One of Dick's letters preserved long after his death shows him to have
been human and unaffected, and gives a good first-hand account of
Crewe in the mid-1880s.
November 26th
Friends of Queens Park have a meeting on
Tuesday 8th December at 6:00 pm at the queens park jubilee Cafe were
everyone is welcome to come along.
Updated the Burma Island page as most of the
work has been done on the island in the last few weeks
The first meeting of the Friends of Queens Park which has
taken over from the Stakeholder
took place on Tuesday night with a trip around the park
to see the progress led by Ian Bright,
from EBM consultants. A lot turned up despite the bad
weather and darkness.

We were shown the new roadway being built by the lake as a
temporary measure so
heavy machinery can move about the park such as diggers
and cranes.

A lot of work has been done on Burma Island and half of the
island has been removed so
it can be rebuilt. All the islands will need most of the
surrounding brick work removed
and rebuilt to prevent collapse

We were then shown Broad walk and the band stand. Most of
the path is full of heavy
machinery and work has been done on the main bridge
which will span the valley to
Coronation Walk. The heavy wooden bridge will be
supported by a large arch and
this time it will be level with steps on one side and a
disabled ramp on the other
so people can get to Coronation Walk. It will all be
replanted.

Its hoped the new bridges will arrive in January- February
and will then be put in
place with huge cranes as the bridge will have to
come in large pieces. It will be
major work to get these cranes into confined spaces but
it is all planned.
The lake area should be open by March and the paths will
be rebuilt as a
temporary measure. In the future the paths will
have to be closed so new
ones can be built once all the work has been done. Its
hoped the lake will
have both boats and fishing once again. There is
problem with having Carp
in the lake but with a new filtering system its
hoped this can be done
There was a big stink at the Queens park today as all the
flowers in the main drive were removed and tons of new soil
and manure were delivered ready for next years growth. So we
should have some good displays next year but in the mean
time the park has some good healthy smells
Down at the lake work was being done on Burma Island and
down by the sluice gates. Wrekins display boards were being
removed at long last. So people can now go down to the park
and see some action at last. Its been a frustrating time for
all and tempers have frayed with no work since early this
year. But at last we can see work being done. Check back for
updates.
Finally dont forget the next meeting
Tuesday, October 20, 2009
Time:
5:30pm - 6:30pm
Location:
Queens Park Cafe, Crewe for a walk around the park ALL
welcome
At the Queens Park today I ran into the lads from
British Military
Fitness They were putting on a corporate event
sponsored by Nokia for a local company. This involves team
building and the
old Military gun run often seen at events. Its good to see
the park put to use for something for a change

At long last a digger was spotted in the Park lake today so work
is under way at last and
we will be following the work with great interest

Its a nice time of year as the Autumn moves in slowly in the
park with beautiful colours of
the trees and some good pictures are possible at this time of
the year so get down to the park with your camera

The new contractor has taken over the lake refurbishment and
everyone is disappointed they cant see any visible signs of
action after a week. The Wrekin signs are still in place and it
was hoped they would have been removed by now.
Over on
Facebook a group of over a 1,200 has formed complaining
about the park. This follows reports in the local paper of the
state of the play area which was highlighted at the Stack
holders meeting. To give everyone time the next meeting which
will be the first for the Friends of the Park is on at Queens
Park Cafe, Crewe
Tuesday, October 20 at 4:00pm and if everyone turns up from
Facebook the park will be full. It promises to be a lively
meeting with complaints about the elections of officers for the
friends of the park as there was no vote taken just a proposer
and seconded
There has been no work visible on site for the bandstand but
much of this work is being done off site and its still on track
to finish in December 2009
The final major part of the railings took place last week and
now all the major work is done its just down to little bits left
to be done which are waiting on other projects
The last Stakeholder meeting took place at the Queens Park
Yesterday Tuesday 15th September. It was a long meeting going on
from 6 o’clock to 8 o’clock with a good turn out. So much was
discussed but the main points were.
The first was the election for officers for the new Friends of
the Queens Park which will now take over from the Stakeholders
and will develop the park and generally see the park through the
restoration and beyond. Anyone who want to join and its open to
everyone should contact
Elaine Dodd
Queens Park Manager
Tel: 01270 537896.
The second most important item which everyone wants to know is
the new contractor is Tolent Construction and there website is
http://www.tolent.co.uk/.
The officers explained that lots of checks and safeguards were
in place to ensure they didn’t fail us like Wrekin did. There
are penalty clauses and deposits to ensure the work is done
correctly and on time. They should be on site by next week and
we hope we can see some action very soon; they will be doing the
bridges, lake etc.

We then had a slide show of the work that had been done so far
which included the work already done on the lake with part of
the wall around the lake already done along with footing for the
bridges etc. The banking along Victoria Ave is finished with a
smoother transition to Coronation Walk and in doing this a lot
of the mud from by the bandstand has been moved and the area
cleared. Other work was the band stand which is on the main site
here .

Concern was expressed at the state of the child play area and it
was planned this would be one of the last things done as it
would be getting a lot of traffic with other work. They did
promise to relook at this due to the complaints about the area
and maybe this can be brought forward.
Plans are being drawn up for the pavilion, bowling green and the
lodges and should be available at the next meeting. The lodges
will be used for park admin and possibly for education purposes
which may contain a mini museum showing the history of the park.
The current occupant of the east lodge is leaving soon after
being there over 40 years.
It was hoped a major event could be organized for a grand
opening of the park in may 2011 and this would be a large scale
event to promote the park
Charter Trustees for unparished areas of Crewe wards south,
north, west and east.
Councillor Jacqueline Weatherill
Home Address:
45 Dane Bank Avenue
Crewe
Cheshire
CW2 8AE
Phone: 01270 569551
jacquie.weatherill@cheshireeast.gov.uk
Councillor Chris Thorley
Home Address:
208 Middlewich Street
Crewe
Cheshire
CW1 4DL
Phone: 01270 581978
chris.thorley@cheshireeast.gov.uk
Councillor
Steve Conquest
Home Address:
6 Ursuline Way
Crewe
Cheshire
CW2 6LB
Phone: 01270 501923
steve.conquest@cheshireeast.gov.uk
Councillor Derek BebbingtonHome
Address:
8a Weaver View
Church Minshull
Cheshire
CW5 6EB
Phone: 01270 522902
derek.bebbington@cheshireeast.gov.uk
Councillor Betty HowellHome
Address:
7 Railbrook Court
Railway Street
Crewe
Cheshire
CW2 7AD
Phone: 01270 584689
betty.howell@cheshireeast.gov.uk

Its all go in the park this week as you can see above the
bandstand work is under way new steel work is already in and
there are 4 men working on the project

Down at Coronation walk they have had to dig a hole into
the mud which they have moved to support the north wall. The
pipe that goes under the lake is blocked not in the park but
outside. They have had to dig to find the problem and
replace the pipe to connect Alton St to Victoria Ave and
beyond

4th August and the final part of the new railings is going in
along Victoria Ave. Apart from a odd few feet the railings are
all now complete there is just the little bit waiting for new
gates before they can do the last little bit.
As you can see above the banking is going great guns and wont be
long before its finished and at the same time the mass of mud
has been moved from by the Bandstand so its real progress.
The date for the next stakeholder
meeting will be Tuesday 15th September, 6pm start, in the Jubilee
Cafeteria. All are welcome, and the next get-together should report
plenty of progress.
The Queens Park project has been surrounded by speculation and
delays. Almost every aspect of the work has had its
complications; however as Cheshire East Council strives forward
it has put measures in place to literally get the earthmoving.
Cheshire East Council is committed to supporting and utilising
local businesses and the economy, the project team of
Consultants and Contractors appointed to date are all North West
based.
This week has seen another local contractor earth moving,
utilising the clay-soil deposits from the debris of the lake, to
form the basis for new raised footpath improving access and
supporting the original failing retention wall, all on the North
West side of the Park.
Even more exciting is that the Cheshire East specialist
restorers ‘ Lost Art’
has been appointed to complete the Bandstand refurbishment and
works commenced this Monday (20th).
At a recent meeting with the Heritage Lottery and Cheshire East
Council all parts demonstrated their commitment seeing the works
progresses and finalised.
As the original contractor went into administration, the project
legalities and the stoppage of works caused frustration, both
within the Authority and to members of the public.
On yet another positive note tenders for completion of the lake
and bridge works have now been returned and are being reviewed
by the Consultants, including the proposed building works
required. It is anticipated that an announcement of the new
Contractor will be made within weeks.
Councillor Andrew Knowles, Health and Wellbeing Portfolio Holder
for Cheshire East Council, said: “I am delighted to see workman
now on site at Queens Park and even more so that local
Contractors and Experts are part of this process. It is a very
exciting time for the Park, the current Bandstand works, which
will be undertaken during the next 20 weeks, utilises the very
best of our North West Craftsmen with their skills and high
quality historically authentic works.”

The work on the banking along Victoria Ave is
well under way but at the moment resembles a mud bath with all the
rain we have had. As well as the rebuilding of the wall they are
moving the mud from the top area near the band stand so its two jobs
getting done

I attended the stakeholders meeting held at the park on
Wednesday 8th July. There has been little or no visible work
done at the park for months but that's all about to change. The
new tender should be opened this week and hopefully a new
contractor appointed very quickly. There has been a delay as
after the tenders were in one contractor reduced the price and
as a result other had to be given the opportunity to resubmit
tenders.
At the meeting the Lions came with some cash to build a sensory
garden like the one a Stapley Water gardens so that is another
new feature which should be a major attractions and as the Lions
are funding it there is no messing about getting the money.
The meeting discussed that the stakeholder work would be done
once the park was finished and then a friends of the Queens Park
would take over to make decisions about the park and see that
its maintained and looked after. This will be open to anyone and
will shortly be setup as a charity so they can get funding for
any future projects.
The work on the wall were the Bats have held up work is now due
to start this week and should be finished in a month. This also
means the railings can then be finished as there is only this
small section to do. We will have pictures as soon as there is
signs of life. Work on the bandstand is also imminent.
The summer bedding is now starting to flower and will soon be in
its full glory as can be seen above taken after the meeting.
The park has events still going on this summer which are
12th July Blozone Band - FAB Blues Band
19th All Sorts Dog Display Team
26th George Formby Ukulele Soc
1st & 2nd Aug TipKinder - Bob Fields GRANDS incl. "The Shanaze
Reade BMX Track"
2nd August The Valentines Duo
9th Tarporley Concert Band
16th Lucy Jane ~ Punch & Judy
23rd Matrix Dancers with Pheonix Disco
Thurs 27th Youth Fire Serv Display
Sat 29th CARNIVAL King George V Playing Fields
Thurs 5th Nov LIONS Bonfire & Fireworks Display
While
its not strictly the Queens Park the new footpath /cycle way is
another major step forward. Costing over 1 million pounds it
will link the Queens Park to Nantwich and means you will be able
to walk or cycle to the park from Nantwich in safety along a
beautiful country path. This should help make the park more
accessible to all. Its hoped the work we have done in trying to
get Tipkinder on the map will come into play as the path can
then be extended via Tipkinder and the Valley Park and take you
into the town centre.

The work to redo the main wall flower bed by Victoria Ave is
under way. This is a triple whammy as to redo the wall they
are using mud that was taken from the lake. This mud has
formed a mountain up near the band stand and as you can see
above they are removing the mountain to use on the wall.

This work had been delayed as there were Bats nesting in
the wall and they couldn't be disturbed. The work should
take about 4 weeks and once that is done they can then
replace the railings at the top. So that's 3 jobs done.
New Ducklings in the park 17 May 2009
Its good to see the wildlife are flourishing even if the park isn't
as new ducklings were spotted in the lake. A few duck still remain and
some even visit Tipkinder

New Park Manager
Elaine Dodd is the new Queens Park manager. The new post is seen as a key role in helping to transform the Victorian park to its former glory.
Delays in the redevelopment project have proved frustrating for the officers involved and loyal users of the park.
It is hoped an announcement will be made shortly as to whom the selected new contractors are who will continue with works stalled when contractor Wrekin went into liquidation.
All that is happening at the park at the moment is the new railings are having their third coat of paint.
|